ROSTAR

Aluminum can factory


Leningrad region, Vsevolozhsk

Construction Time

12 months
August 2002 - September 2003

Step Services
Total Area
23 500 sq. m
STEP appeared as the General Contractor on Design and Construction for ROSTAR – a Packing Division of the Russian Aluminium Company.

Works were performed on the territory in the area of about 10 hectares. The total area of the new plant facilities is 23 500 sq. m: the production building occupies 12000 sq. m, the area of the storage building is 11500 sq. m.

Design and construction works, improvement of the territory, arrangement of engineering communications and construction of the access roads were completed in 15 months.

The aggregate investment in the new production is $100 mln. Investments in construction came to approx $12.5 mln.

The project was realized in common with the Roeslein & Associates American engineering company, manufacturers of equipment from the USA (Sequa Can Machinery and Belvac Production Machinery) and Germany (ITS GmbH, NSM Magnettechnik GmbH&Co).