The Concentrate shipment facility project (JSC Kola MMC) is prepared for substantial completion.

December 12, 2019
At the moment work on the technical re-equipment and construction of the complex for nickel concentrate shipment obtained by processing of disseminated copper-nickel ores is almost complete.
Commissioning work on technological equipment was carried out at the facility.
The customer carries out comprehensive tests on operating environment. It is planned to achieve the project parameters of the installation as a whole by January 15.